Skip to main content

House Owners Email Response- Anonymous Detailings

With References of [1] the responses received from different owners are shared publicly for all. 


06th EMAIL

For placing the transformer at back side of plot no 1 to 8 is not acceptable.  03-09-2023


05th EMAIL

As requested by our president I am here furnishing my opinion regarding the transformer installation location.

I strongly oppose the installation behind the plots 1 to 8 as it's intended for park area. 

I am the owner of plot 2 and I Prajay collected additional amount to buy this plot mentioning it as park facing. So, I don't want any dangerous things like transformers to be installed in that designated area as it can risk the lives of children and other society people who would use the park in future. 

Would request the society leadership team to make sure to address this issue and place the transformer in a different location. 03-09-2023

04th EMAIL 

By observing the location and power supply units in various gated communities, I feel and recommend to install the transformar in the same place and can be isolated with proper barrier for the safety of the visitors in the park. 03-09-2023

03rd EMAIL

The area behind houses 1..8 is clearly designated for park as per approved layout. We will object to substation being installed there.

I took the plot because the park was behind it.   02-09-2023

 

02nd EMAIL 

I get to know that prajay management has decide to install a transformer in a designated area for park behind plot 1 to 8.

 

I am owner of Plot no.1 and as per the agreement I entered with Praja this area designed for park and now it's nature is goin to be changed, which is not acceptable.

 

I am requesting you all to please oppose this and arrange a place on Prajay land instead of a common place.

 

If final decision goes against the sale agreement, I am fine to take this matter legally in court.    30-03-2023

 

01st EMAIL

I don’t have any objection..regarding safety it is underground work so worries and if something has to happen it will happen ..and feeder is near to that area (park)so it’s a best place and it will also help to stop the encroachment by some owners.30-03-2023

[1] https://www.blogger.com/u/1/blog/post/edit/638192802341875394/1804496801011638113

Comments

Popular posts from this blog

Maintenance issues - Prajay Water Front City Phase 02, Shamirpet, Hdyerabad

    011- The majority  of house owners are in favor of giving maintenance dues to society accounts only and making society as accountable as well. If the owner pays to Society, then once a month by Society account, we could pay you whatever maintenance dues are received monthly. Initially, it will be a little hard, but soon it may get streamlined with the support of Prajay staff and EC member coordination. we are seeking your opinion on this line .   022-    While  collecting the response from owners via GBM, door-to-door, and one-to-one calls, we came to know that many of the houses are still a year in duration, and they paid already for a year advance during handover. So, Society would like to know How many houses are eligible to participate in the maintenance dues?  A detail of houses and their owner’s information will help us to quickly connect and brief the builder’s proposal and society's opinion on that.     033-    In the present scenario, society would like

Minutes of meeting with Managing Director Sri Rohit Reddy & Prajay Waterfront City Phase 02 Society Members

  Minutes of meetings with Managing Director Sri Rohit Reddy & Prajay Waterfront City Phase- 02 Society Members.        The information of meeting attendees is given below: 1.     Sri Rohit Reddy, Managing Director, PRAJAY 2.     Vijender Kumar Solanki, General Secretary 3.     Vinay Babu , Joint Secretary 4.     Kanka Raju, Director 5.     G. Krishnama Charyulu Owner House no 11 & 12     Agenda of Meeting: 01- Maintenance  02-  Past Maintenance Dues 01- Maintenance - The Discussion started with the maintenance agenda, Vijender Kumar Solanki stated that based on the call of maintenance, Society received input through various modes including GBM, and found the opinion of the owner who may agree in the band of 300-500 INR at a maximum only. In the reply of GS, The Managing Director briefed that at present, the Prajay waterfront city phase 02 development is at good heights, and owners must come forward to pay maintenance, which is due for long period

Proposed Amendement - (PWFCP2-BY-LAW's) To Be Placed Before Director meetings Followed by GBM

PRAJAY WATERFRONT CITY PHASE-02  DRAFT PROPOSAL                                              By-Laws Amendments Proposal   01-    Nomination   1.1    Let the sale deed holder and registered society member only be eligible for nomination. In special cases, if any family member is interested in nominating themselves, such case Will Deed/GPA or a Copy of NOC is required, and its approval is subject to DIRECTOR's APROVAL followed by placing before GBM approval for sending to nomination. 1.2 For fair negotiations with the builder, the nominating person must not take up any job( paid or honorary) with the builder( prior to six months) or the society-related clerical or supervisory jobs. After the complete handover of the project, members may take up a job with the builder.   02-    Self-Declaration   2.1    - A director member who is interested in nominating must declare to devote a minimum of 30 Hours of community service in a month, irrespective they are residing in P